Guangdong Power Plant Desulfurization Wastewater Treatment Project

Project Photos
Project Overview

The desulfurization wastewater of Guangdong Huaxia Yangxi Power Plant Phase II Units 5 and 6 (2*1240MW) Project Zero Discharge of Desulfurization Wastewater EP General Contracting Project is treated by Jiarong Technology Reverse Osmosis (STRO+DTRO) treatment system with high-fold concentration technology to reduce the volume of wastewater.

Project Parameters

Treatment capacity: 48m³/h

Treatment process: pre-treatment + TMF + STRO + DTRO + slag flushing

Raw water TDS: 30-55g/L

System recovery rate: 60-75%

Desalination rate: 95-96%

Design pressure: 90 bar

Operating pressure: 65-80 bar